About the Project

In an ongoing effort to provide quality wireless service, Verizon Wireless and T-Mobile has identified your community as one that will benefit from improved network coverage. 

Milestone Towers is proposing a wireless telecommunications facility at Notre Dame Preparatory School, addressed 815 Hampton Lane, Towson, MD 21286. 

The proposal is for a 150-foot monopole and will include ground equipment required to operate the facility. 

This equipment will be located at the base of the structure in a secure fenced area. Verizon Wireless and T-Mobile will be the first wireless carriers to locate on the proposed tower.

Update #2: Thank you to those who attended the Milestone Towers community meeting on November 4. Please click here to view the online Town Hall presentation. We appreciate all feedback and will look to provide future updates on the project website and email updates to those who attended and provided their email address. If you would like to be on the email list for project updates, please send a comment through our contact form and we’ll add your contact information to the email list.

At the meeting, the question of photo renderings was raised. The renderings shared were developed using existing street view imagery during “leaf-on” foliage time. We will update the website once foliage has fallen off in the next month using photos taken from the same vantage points.

Update #1: Upcoming community event:

Online Town Hall: On Tuesday, November 4th @ 6:00 pm we will hold an online Town Hall webinar consisting of a short presentation followed by a question and answer time. Registration is required and can be completed on the Town Hall page.

Our Process

1. Due Diligence 

Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.

2. Land Use

Tower Committee and Special Exception Applications, Community Meeting, Staff Review.

3. Permitting

Conduct Bid Walk With Contractors and school representatives, submit Site Plan and Building permit applications.

4. Construction 

Tower construction = 4-6 weeks  | Carrier construction = 4-6 weeks on average

On-site supervision by Construction Manager | Schedule with schools to minimize disturbance to student activities.

 

5. Site Maintenance

Four visits per year for site maintenance | Remove trash, debris, check signage. 

Annual RF testing | 2-4 visits per year for carrier modifications. 

About Us

With over 20 years experience, Milestone Towers is the leading developer of wireless infrastructure and cell towers in partnership with school, government and utility landowners.